Sub-Contractor receives settlement of £245,000 payment dispute.
Summary A Sub-Contractor submitted its Payment Application valuing its payment amount due at £245,000, but received a Payment Notice from...
Mark Holden-Smith
16 hours ago1 min read


Managing Risks under NEC - Practical Guidance
Without professional guidance, it can be difficult to know where to start with the management of risks through NEC3 and NEC4 Engineering...
Mark Holden-Smith
Feb 152 min read

Navigating Adjudication Processes in Construction Disputes
Welcome to our short guide on navigating adjudication in construction disputes.
Mark Holden-Smith
Sep 2, 20242 min read

How To Quantify Loss & Expense Claims
Here is a short guide, with key considerations, on how to quantify loss & expense claims.
Mark Holden-Smith
Aug 28, 20246 min read


Here is how we helped a Subcontractor settle a dispute of £288,000 concerning suspension, repudiatory breach, termination, adjudication, and a settlement agreement all in the same dispute!
Here is how we helped a Subcontractor settle a dispute of £288,000.
Mark Holden-Smith
Mar 22, 20243 min read


Delay Analysis: A basic approach to quantum
Here is a basic approach to quantifying a claim for delay.
Mark Holden-Smith
Mar 21, 20242 min read

£740,000 valuation dispute resolved for our client in Adjudication.
Here is a short post on how we resolved a complex and high value dispute for our client using Adjudication .
Mark Holden-Smith
Mar 14, 20242 min read


£400,000 payment procured for Delay, Disruption and Variations Dispute
Overview The client received a Payless Notice giving a payment of just over £8,000.00, which it disputed, and we were instructed to...
Mark Holden-Smith
Nov 14, 20231 min read

Whats the Issue? - A Guide to Formatting a Coherent Claim
Introduction The purpose of this guide is to explain and discuss an approach and format that can be used to clearly and coherently draft...
Mark Holden-Smith
Nov 13, 20235 min read


£600,000 for delay procured for our client without Adjudication.
Overview Holden Smith Consultancy (HSC) were commissioned to provide professional judgment on the true value for the sum due as loss and...
Mark Holden-Smith
Apr 10, 20231 min read


Dispute resolved concerning valuation, delay & disruption and a £150,000 payment procured
Overview Holden Smith Consultancy (HSC) were commissioned by its client who disputed a valuation in a Payless Notice it received that...
Mark Holden-Smith
Apr 5, 20231 min read


£56,000 dispute resolved concerning true value, delay and termination.
Holden Smith Consultancy Ltd (HSC) were employed to evaluate and manage a dispute that arose between two parties concerning a disputed...
Mark Holden-Smith
Mar 22, 20231 min read


Dispute avoided concerning Extension of Time with costs
Brief Overview Our client (the Sub-Contractor) received a payers notice that included a payment of £nil for its losses incurred through...
Mark Holden-Smith
Feb 20, 20232 min read


We defended our client in Adjudication against a £1.3M damages claim for wrongful termination
This post provides a brief overview of a defence prepared by Holden Smith Consultancy for a client who received a claim for damages...
Mark Holden-Smith
Feb 20, 20232 min read


Dispute avoided concerning omission of works and loss of profit
Overview Our client (a Sub-Contractor) had parts of its contract works omitted by the Contractor and given to other Sub-Contractors, and...
Mark Holden-Smith
Feb 20, 20232 min read


£300,000 loss & expense payment procured for our client without a dispute
Introduction Our client (the Sub-Contractor) had its claim for extension of time and loss and expense rejected by the Main Contractor,...
Mark Holden-Smith
Feb 20, 20232 min read


£75,000 payment for disruption agreed without Adjudication
Overview Our client (the sub-contractor) received a Payless notice showing a difference of £75k, and we were instructed to procure a fair...
Mark Holden-Smith
Feb 20, 20231 min read