Overview
Holden Smith Consultancy (HSC) were commissioned to provide professional judgment on the true value for the sum due as loss and expense for delay suffered by its client.
The process
HSC reviewed the terms of the contract and identified the specific requirements for, and managed the procurement of, key evidence. HSC assessed the evidence which included the carrying out of factual demonstrations concerning planned and actual progress and productivity in a delay analysis. The results of the assessment were evaluated in accordance with the contract and relevant legal principles to arrive at quantum for the sum due for delay as Prolongated Preliminaries and a Preliminary Thickening.
Result
The claim was submitted and after a period of negotiation HSC client received payment of £600,000 for the claim without the need for Adjudication to the benefit of all stakeholders in the avoidance of a dispute.
Contact Us for a Free Review
If we can assist you in any type of construction claim do not hesitate to get on touch for a free preliminary review of the problem.
Tel: 07834284308
Email: mark@holden-smith.com
Commentaires